June 18th – 2nd stage of the gas pipeline from Vaca Muerta to Litoral Argentina

2nd stage of the gas pipeline from Vaca Muerta to Litoral Argentina

June 18th 2024

2nd stage of the gas pipeline from Vaca Muerta to Litoral Argentina

 

National Holidays:

June 17th, 20th and 21st

 

Grains and Markets:

South Korea’s MFG has purchased 60,000 tons soya bean meal on October dates.

Taiwan has purchased 65,000 tons of maize to be sourced from Brazil on August dates.

Morocco is in the market for wheat, Supramax volume during August.

 

2nd stage of the gas pipeline from Vaca Muerta to Litoral Argentina:

The 2nd stage of the gas pipeline that will feed Vaca Muerta gas to Litoral Argentina is soon be tendered out by the Government.

This stage will be 484 km in length and will run from Saliqueló to San Jeronimo.

Pipes from the 1st stage were imported from Brazil, through Buenos Aires Dock Sud, in uncoated condition.

The pipes are estimated to be 36 inches in length, 12 meters long and each one weighing in at about 5 tons.

180624 2nd stage of the gas pipeline from Vaca Muerta to Litoral Argentina

STS BUNKER AT ZONA COMUN FOR NEXT DAYS:
As always, the STS operation is up to the discretion of the Masters of the vessels involved.

As always, the STS operation is up to the discretion of the Masters of the vessels involved.

 

Will keep you posted.

Best regards,

Antares Servicios Maritimos S.A.

For more information

Local News